RVNL Advances Orange Line of Kolkata Metro Towards Crucial Phase

Date:

Rail Vikas Nigam Limited (RVNL) has achieved a significant milestone in the construction of the Orange Line of the Kolkata Metro by completing the basic work for the underground tunnels along the median of VIP Road. The progress covers a 72-meter stretch, preparing the project to curve towards the airport in its crucial next phase.

To ensure minimal disruption on the vital VIP Road, RVNL has devised a phased construction approach for the New Garia-Airport Metro corridor. A new road stretch has been developed to facilitate Kolkata-bound traffic, and a five-day traffic trial is expected next week. Following successful trials, Bidhannagar traffic authorities will hand over the site for the next stage of construction.

The mostly elevated 29-meter Metro corridor transitions into its final leg, where a 300-meter ramp and 500 meters of twin underground tunnels will be built using the cut-and-cover method. This segment, executed by contractor Afcons, is critical to connecting the city seamlessly to the airport.

The Orange Line project signifies RVNL’s commitment to efficient urban connectivity while mitigating traffic challenges, ensuring Kolkata’s commuters experience minimal inconvenience during this transformational infrastructure development.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

eight + 12 =

spot_img

Share post:

More like this
Related

The UAE’s Sand Could Change How We Build

The UAE’s latest innovation offers an inspiring example of...

India’s Building Materials and Interiors Industry Comes Together at MATECIA 2026

MATECIA Exhibition 2026 has been inaugurated at Yashobhoomi, New...

India Plans $1.2 Billion Push to Build Advanced Construction Equipment Locally

India is preparing a $1.2 billion incentive scheme to...

77% of Occupiers to Expand Office Portfolios in India, Says CBRE

India’s office real estate market is expected to maintain...